The project is at an advanced stage of development where Tractabel was appointed to finalise the Pre-FEED for the project. The site has been identified and land was identified and secured for the project. Two wind masts we installed for the measurement campaign. The engagement with authorities was established and Law 13-09 procedures have started. The hydrogen off-take agreement is at an advanced stage with a newly to be established car frame European manufacturer for the entire production of green hydrogen. The plan is for the car frames to be exported to Europe.
PRE-FEED
FINAL PRODUCT
28,000 Mtpa GREEN HYDROGEN PEROXIDE
ELECTROLYZERS CAPACITY
400 MW
RENEWABLE ENERGY CAPACITY
700 MW (60:40 WIND:SOLAR)
OFF-TAKER
LOCAL OFF-TAKERS
EXPECTED CAPEX
$1.1 Billion
LOCAL PARTY
FIRSTWIND
EXPECTED COD YEAR
2028